Building D
Soon a new building for students
Summary of recent chronology :

19/04/2011: Opening the construction site
06/15/2011: Call for tender for general contractor (GC)
05/07/2011: Signing of the Convention CUG - Association of neighbors of the Tavan Road
21/07/2011: Answers to GC
22/08/2011: Start of excavation by Grisoni-Zaugg
23/09/2011: Deadline for return of tenders general contractors
27/09/2011: Opening of tenders general contractors
09/28/2011: End excavation work phase 1 (Grisoni-Zaugg)
13/10/2011: Hearing of general contractors
20/10/2011: Choice of Implenia General Contractor Ltd.
07/12/2011: Public meeting with FRAR and Implenia
19/04/2011: Opening the construction site
06/15/2011: Call for tender for general contractor (GC)
05/07/2011: Signing of the Convention CUG - Association of neighbors of the Tavan Road
21/07/2011: Answers to GC
22/08/2011: Start of excavation by Grisoni-Zaugg
23/09/2011: Deadline for return of tenders general contractors
27/09/2011: Opening of tenders general contractors

09/28/2011: End excavation work phase 1 (Grisoni-Zaugg)
13/10/2011: Hearing of general contractors
20/10/2011: Choice of Implenia General Contractor Ltd.
07/12/2011: Public meeting with FRAR and Implenia
29/02/2012 : Installation site board
08/03/2012 : Geotechnical measurements along Edouard-Tavan road
12/03/2012 : locker room roof destruction
19/03/2012 : Begining of structural work (installation of Girsoni-Zaugg)